Santa Rosa Memorial Hospital Central Processing Renovations

Location: Santa Rosa, California

Project Team: TLCD Architecture, NM&R Architects, Eclipse Mechanical Engineers

Renovations conisited of 40 new patient rooms with all new assoiciated medical systems and utilities. Over an eleven-month construction schedule, the project was broken into seven phases to fit constraints held by the client. The area in the hospital had to remian opertational at all times which required a temporary infection control barrier that had to be taken down at the end of every shift then reinstalled the next day. Careful and responsive project manegment was imperitive given the complicated nature of the project. The teams had to use a lot of problem solving stratiegies during construction necessating them to working through the night and weekends. The final outcome was a successful OSHPD approved project completed on time and under budget.